Florence, S.C. — The City of Florence has launched a \$450,000 Hoffmeyer Road sewer fix, with overnight construction that began Monday, Oct. 12.
A contractor will work overnight from 6 in the evening until 6 in the morning to limit daytime traffic disruption. The first step is inspecting and assessing the existing West End sewer main, expected to take about three to five days.
The work follows repeat sewer trouble earlier this year — blockages and foul smells. Assistant City Manager Clint Moore said a Hoffmeyer Road blockage has required temporary bypass pumps, and the project is meant to fix current problems while preparing for future growth.
Crews expect two to three point repairs, digging up and replacing specific sections of the main. After that, they will use a trenchless method — either pipe-burst installs of new HDPE pipe or an epoxy fiberglass liner inside the old pipe.
Traffic control will appear only where crews are working and will move as the job progresses. Work is starting in the Five Points area and will move along Hoffmeyer Road toward Darlington Street. Florence runs a council-manager form of city government.